How to Write a Project Plan, Step by Step

AdeptWrite Editorial TeamUpdated 8 min read

A project plan is a document that says what the project will deliver, why, who does what, by when, with which resources and what could go wrong. Write it by stating the goal, fixing the scope, listing deliverables and tasks, assigning owners, setting dates, estimating cost, and recording risks. Keep it short enough that the team will read it.

What a project plan does

A project plan is the working document that turns an idea into a set of agreed actions. It answers the questions every team member and sponsor will ask sooner or later: What are we building? Why? Who is responsible for each part? When is it due? What will it cost? What might go wrong?

A good plan is not a long essay. It is a clear, current reference that people actually open. If your plan is too heavy to read, nobody will use it, and its main purpose, keeping everyone aligned, is lost.

Project plan vs similar documents

People often confuse the plan with neighbouring documents. This table shows how they differ.

DocumentMain questionLevel of detailWhen it is written
Project proposalShould we do this?Persuasive, high levelBefore approval
Project charterWhat has been approved?Short: goals, sponsor, limitsAt approval
Project planHow will we deliver it?Detailed: tasks, owners, datesAfter approval, before work
Schedule or timelineWhen does each thing happen?Dates and dependenciesPart of the plan
RoadmapWhere is the product heading?Broad, over a longer periodOngoing

If you still need approval, start with a project proposal. If the project is already approved, you are ready for a plan.

What goes into a project plan

Most plans answer three groups of questions. You do not need every item for every project: a small internal job may fit on two pages, while a large one needs more.

GroupSectionsThe question it answers
Why and whatSummary; goals and success measures; scope (in and out)What are we doing, and how will we know it worked?
How and whenDeliverables; tasks and milestones; owners and roles; scheduleWho produces what, and by which date?
What could change itBudget and resources; risks and assumptions; communication; change processWhat do we need, what might go wrong, and how do we handle changes?

Write the first group before anything else. If the team cannot agree on the goal and the scope, detailed tasks and dates will only hide the disagreement until it surfaces later as delay.

How to make a project plan, step by step

Step 1: Write the goal in one sentence

Begin with the outcome, not the activity. "Launch the new help centre" is an activity. "Reduce the number of basic support questions by making answers easy to find" is a goal. Add how you will measure it: a number, a date or a yes/no test.

Step 2: Draw the boundary around the work

Write what is in scope and what is out of scope. Out-of-scope items prevent later arguments. For example: "In scope: rewrite 40 existing articles. Out of scope: building a new search engine."

Step 3: List the deliverables

Deliverables are the concrete things you will produce. Make each one checkable: a document, a feature, a report, an event. If you cannot tell when it is finished, rewrite it until you can.

Step 4: Break the work into tasks

Divide each deliverable into smaller tasks until each one can be done by one person in a few days. Start each task with a verb: draft, review, test, publish. Smaller tasks are easier to estimate and easier to track.

Step 5: Put the tasks in order and estimate them

Note which tasks depend on others. You cannot publish before you review, and you cannot review before you draft. The chain of dependent tasks that decides the earliest finish date is often called the critical path. Delay on this chain delays the whole project, so watch it closely.

For the estimates, ask the people who will do the work. Add a buffer for review, approvals and surprises. Be honest: an optimistic plan that fails is worse than a cautious one that holds.

Step 6: Name an owner and a date for each piece

Give every task one named owner. A shared task is often a forgotten task. If several people take part, still name the person responsible for the result.

Then set milestones. Milestones are checkpoints that show real progress, such as "Draft approved" or "Pilot complete". Use specific dates, not "mid-month", and confirm them with owners.

Step 7: Estimate the budget and resources

List people's time, software, outside services and other costs. Show assumptions, such as hourly rates or tool prices, so reviewers can check them.

Step 8: Identify the risks

Ask: what could delay or damage this project? For each risk, note the likelihood, the impact, and what you will do about it.

Step 9: Plan communication and changes

Decide who receives updates, how often and in what form. Also decide how changes to scope, schedule or budget will be approved. Without this, a project quietly grows.

Step 10: Review and approve

Share the draft with the sponsor and the team. Ask for corrections, record the approved version and give it a version number and date.

Worked example (invented)

Here is a compact plan for a fictional project.

Project: Rewrite the customer help centre
Goal: Help customers find answers without contacting support, measured by a lower share of repeat basic questions after launch
Sponsor: Priya Nair, Head of Support
Project lead: Omar Haddad

Scope

  • In: review and rewrite 40 articles, add a "start here" page, update screenshots
  • Out: new search technology, translation into other languages

Deliverables: audit spreadsheet, 40 revised articles, new start page, launch note

MilestoneOwnerDate
Audit finishedOmar12 February
Style guide agreedLena19 February
20 articles revisedTeam12 March
All articles reviewed by supportPriya26 March
LaunchOmar2 April

Budget: staff time only; screenshot tool licence already owned

RiskLikelihoodImpactResponse
Support team busy during quarter endHighMediumSchedule review slots in advance
Product changes make screenshots outdatedMediumMediumTake final screenshots in the last week
Reviewer unavailableLowHighName a deputy reviewer

Communication: short written update every Friday; steering check-in at each milestone

This is only one page, yet someone who has never heard of the project can read it and understand what is happening.

Writing tips for a plan people will use

  • Lead with the summary. Readers should understand the project in a minute.
  • Use tables for tasks, dates and risks. They are easier to scan than paragraphs.
  • Write short, active sentences. "Omar drafts the style guide" is clearer than "The style guide will be drafted."
  • Use the same names for things throughout. Do not call the same deliverable by three names.
  • Show assumptions. If the dates depend on a supplier, say so.
  • Keep a version history. A date and a one-line note about what changed is enough.

If your first draft is too long, the Text Summarizer can help produce a summary paragraph that you edit, and the Outline Generator can draft section headings from your notes. Always check numbers and dates yourself.

Common mistakes

  1. Vague goals. "Improve the website" cannot be measured.
  2. No out-of-scope list. Unlimited scope is the usual cause of delay.
  3. Tasks without owners. If everyone owns it, no one does.
  4. No buffer. Plans with every task on its minimum time often slip.
  5. Ignoring risks. Writing them down makes them manageable.
  6. A plan nobody updates. A plan is only useful if it matches reality.
  7. Too much detail too early. Plan the next few weeks precisely and the later phases more broadly.

Checklist before you share the plan

  • Is the goal clear and measurable?
  • Are scope and exclusions written down?
  • Does each deliverable have a clear finish line?
  • Does each task have one owner and a date?
  • Are risks and assumptions listed?
  • Is there a plan for updates and changes?
  • Has the sponsor reviewed it?

For adjacent documents, see how to write a one-pager, how to write a meeting agenda and how to write meeting minutes. To check how easy your plan is to read, the Readability Checker runs in your browser, and the Grammar Checker can tidy the wording.

Try the tools

Outline Generator
Build an article, essay, thesis or presentation outline from a single topic.
Open tool
Text Summarizer
Summarize long text into the key points.
Open tool
Readability Checker
Measure how readable your text is for your audience.
Open tool
Grammar Checker
Fix grammar, spelling and punctuation in English and other languages, with every change highlighted.
Open tool

Frequently asked questions

What should a project plan include?

At minimum: the goal and success measures, scope, deliverables, tasks with owners, a schedule with milestones, budget or resources, risks and a communication plan. Add a change process for larger projects.

How long should a project plan be?

As long as it needs to be and no longer. A small project may need one or two pages, a large one more. If people stop reading it, it is too long.

What is the difference between a project plan and a project charter?

A charter is a short document that records the approved goals, sponsor and limits. A plan is more detailed and explains how the work will be done, by whom and when.

How often should a project plan be updated?

Review it whenever scope, dates, budget or risks change, and at each milestone. Keep a version number and date so everyone knows they are using the current one.