How to Write a Project Charter (Template)
A project charter is a brief document, usually one or two pages, that states why a project exists, what it will and will not deliver, who is involved, and who has approved it. To write one, answer ten questions in plain language, get the sponsor's sign-off, and keep it as the reference when scope questions arise.
A project charter is the short agreement that lets a project start with everyone pointing in the same direction. It records why the work is worth doing, what is in and out, who is responsible, and who has given permission to proceed. It is deliberately brief: if it needs twenty pages, it has become a plan.
What is a project charter, and how is it different from a plan?
The charter answers "should we do this, and on what terms?" A project plan answers "how exactly will we do it, step by step?" The charter comes first, is written at a high level and changes rarely. The plan is detailed and changes often.
In formal project management, the charter also has an authorising role: it is the document that officially starts the project and gives the project manager the authority to use the organisation's people and money on it. Until the sponsor approves it, the project is still only an idea.
| Document | Main question | Typical length | Changes |
|---|---|---|---|
| Project proposal | Why should you approve this? | Several pages, persuasive | Until a decision is made |
| Project charter | What have we agreed to do? | One to two pages | Rarely, with sponsor approval |
| Project plan | How and when will we do it? | As long as needed | Constantly |
A proposal argues for the project; the charter records the decision once it is made. If you need either, see how to write a project proposal and how to write a project plan. Some organisations use slightly different names or merge documents, so follow your own organisation's format where it has one.
What goes in a project charter?
These are the parts that matter in most teams. For each one, the table gives a test for whether you have written it well.
| Section | What to write | Quality test |
|---|---|---|
| Project name and summary | A plain title and two sentences on the work | A newcomer understands it without help |
| Purpose and background | The problem or opportunity behind the project | Names a real need, not a vague aim |
| Objectives | The outcomes you want, in measurable terms | Someone could check at the end whether each was met |
| Scope: in | What the project will deliver | Specific nouns, not "improve things" |
| Scope: out | What it will not do | Names at least one thing people might assume |
| Deliverables | The things handed over | Each can be recognised when done |
| Stakeholders and roles | Sponsor, project lead, team, key reviewers | Each person has a defined responsibility |
| Timeline | Start, end and key milestones, at a high level | Dates or ranges, not details |
| Budget and resources | Money, people, tools, as an estimate | Says how firm the figures are |
| Assumptions and constraints | What you rely on and what limits you | Each can be wrong, and you can check it |
| Risks | The main things that could go wrong, with a first response | Top few only |
| Approval | Names, roles, date of sign-off | Real signatures or recorded approvals |
How do you write one, step by step?
1. Start with the problem, not the solution
Write one paragraph describing what is wrong or what could be better, and who is affected. A charter that opens with the solution makes it hard to judge later whether the solution worked.
2. Turn the goal into objectives you can check
Replace "improve customer support" with something observable, such as "reduce the time to first reply on support emails" together with a target and a date once you have a baseline. If you do not yet know the baseline, say so and make finding it the first task. Never invent figures to make the charter look precise.
3. Draw the scope line in both directions
List what is in. Then list what is out. The "out" list prevents most arguments later, because a request that appears there can be handled as a change rather than an assumption.
4. Name people and their roles
Identify the sponsor (who approves and resolves priority conflicts), the project lead (who runs it day to day), the team, and the people who must be consulted. Use names, not departments, wherever you can.
5. Set rough timing and budget
Give start and end dates, a handful of milestones and an estimate of cost and effort. Label each as "estimate" or "fixed" so readers do not mistake a guess for a commitment.
6. List assumptions, constraints and risks
An assumption is something you are relying on ("the supplier will deliver by the end of the second month"). A constraint is a limit ("no extra hiring"). A risk is something that might happen ("the key person leaves"). Keep the list short and note a first response for each risk.
7. Review, sign and share
Ask the sponsor and the main stakeholders to read it and to say what is missing or wrong. Record the approval and send the final version to everyone named. Keep it somewhere easy to find.
Project charter template
PROJECT CHARTER
Project name:
Date / version:
Sponsor: Project lead:
- Summary (two sentences)
- Purpose: the problem or opportunity
- Objectives (measurable, with how we will check)
- In scope
- Out of scope
- Deliverables
- Stakeholders and roles
- Timeline: start, end, milestones
- Budget and resources (estimate or fixed)
- Assumptions and constraints
- Main risks and first response
- Approval: name, role, date
Worked example (invented)
A fictional example for a small organisation moving its help articles to a new platform.
Project name: Help-centre move
Summary: Move the existing help articles to a new platform and retire the old one by the end of the planned period.
Purpose: Staff spend time answering the same questions because articles are hard to find. The old platform is no longer supported.
Objectives: (1) All articles in use are available on the new platform. (2) Search finds the ten most common topics on the first results page, checked by a short test by the team. (3) The old platform is switched off.
In scope: Review of existing articles, transfer of those still needed, redirects from old addresses, short training for the support team.
Out of scope: Writing new articles, translating articles, redesigning the company website.
Roles: Sponsor: head of support. Lead: knowledge manager. Team: two support agents and one web developer. Consulted: legal reviewer for policy pages.
Risks: Some articles may be out of date (first response: review them before transfer). Redirects may break links (first response: test a sample before launch).
Approval: Sponsor sign-off recorded with date.
Notice how much the "out of scope" line does: if someone later asks for translations, there is already an answer.
How do you keep the charter useful?
- Write in plain language and short sentences; the Readability Checker runs in your browser and shows whether sentences are getting heavy.
- Use the charter in kick-off meetings and in change requests: "Is this in the charter?" settles most arguments.
- Update it only through the sponsor. A charter that anyone can quietly edit is not an agreement.
- Pair it with a short agenda and recorded decisions; see how to write a meeting agenda.
If you want a first draft of an outline, the Outline Generator can propose sections from a short description of the project. It is an AI tool that needs a free account, and you still need to supply real facts and dates yourself.
Common mistakes
- Making it too long. A charter that cannot be read in five minutes will not be read.
- Vague objectives. "Better, faster, cheaper" gives no way to check success.
- No "out of scope" section. This invites scope creep.
- Invented numbers. A budget or target with no basis misleads everyone.
- No named sponsor. Without one, nobody can resolve priority conflicts.
- Treating it as a one-time formality. It is a reference to return to.
Final checklist
- Purpose describes a real problem
- Objectives can be checked
- Scope lists both in and out
- Every role has a name
- Estimates are labelled as estimates
- Risks and assumptions are short and honest
- Approval is recorded
Try the tools
Frequently asked questions
Why write a project charter at all?
The reason is to record, in a few pages, why the project exists, what it will and will not deliver, who is responsible and who has approved it. It gives the team a shared reference when questions about scope or priority come up.
Who writes the project charter?
Usually the project lead or manager drafts it with input from the sponsor and key stakeholders. The sponsor, or another person with authority over the project, reviews and approves it. Practice varies between organisations, so follow your own process.
How long should a project charter be?
Typically one to two pages. Large or high-risk projects may need more, but the detail belongs in the project plan. If your charter is long, check whether you are describing how instead of what and why.
Can a small project do without a charter?
Very small, low-risk work can run on a short written agreement, even an email that states the goal, scope, owner and deadline. The more people, money or risk involved, the more a proper charter helps.
Related guides
- How to Write a Project Plan, Step by Step — A project plan is a document that says what the project will deliver, why, who does what, by when, with which resources …
- How to Write a Project Proposal: Sections, Template and Example — A project proposal asks a specific reader to approve a project, a budget or both. Start by naming the decision you need,…
- How to Write a Meeting Agenda (With Template and Examples) — A meeting agenda is a short plan that states why people are meeting, what must be decided or discussed, who leads each i…
- How to Write a Memo: Format, Three Examples and a Fill-In Template — A memo is a short, internal document that opens with a header block (To, From, Date, Subject), states its purpose in the…
- Concise Writing: What It Is and How to Do It — Concise writing gives the reader everything they need in as few words as possible, without losing clarity or tone. It is…